| Location: |
3000 Merivale Road, Ottawa, Ontario |
| Owner: |
Minto Commercial Properties Inc. |
| Project Value: |
$55,000,000 |
| Completion Date: |
March 2011 |
Duration: |
4 years |
 |
| More Pictures (rollover thumbnails to view larger image): |
|
|
| |
| |
|
| |
Project Team: |
| Architect: |
HOK Architects Corporation |
| Interior Designer: |
HOK Architects Corporation |
| Structural Engineer: |
Cunliffe & Associates |
| Mechanical Engineer: |
Smith & Andersen Consulting Engineering |
| Electrical Engineer: |
Fox Engineering |
| Civil Engineer: | Novatech Engineering Consultant |
| Landscape Architect: | D & G Landscaping Inc. |
|
| Project Details: |
|
In November 2007, as Project and Construction Manager for Minto Commercial Properties Inc., Ron Engineering commenced the first phase of the Base Building renovations at 3000 Merivale Road. This 1 million sf office complex consists of eight interconnected buildings. The initial work included the demolition of previous tech labs in preparation for the future fit-up of office space. This is a multi-phased, 4 year project that includes 2 base building phases, and 4 fit-up and multiple exterior siteworks phases. As of August 2010, the project is 65% complete. Overall substantial completion is scheduled for March 2011. |
| |
|